Work on two of Port of Auckland’s major infrastructure projects continues to make strong progress, with the first concrete deck pour completed at Bledisloe North wharf and construction advancing on the new international cruise terminal.

The first concrete pour for the Bledisloe North wharf deck covered 1,255m² over a 13-hour continuous pour.

It was the first of eight pours planned as the wharf deck takes shape. The project is expected to reach halfway complete by Christmas. When finished, the wharf deck will use approximately 2,410m³ of concrete, roughly enough to fill an Olympic-sized swimming pool.

At the new Auckland International Cruise Terminal, work is also progressing across the building. The framing, ceiling GIB, suspended ceiling and bulkhead ceiling installation have been completed, along with HVAC ductwork and electrical and data work well progressed. 

Port of Auckland CEO Roger Gray says the progress shows the two connected projects are moving closer to completion.

“We’re getting on with our big build to grow cruise for the city and our team is making stunning progress, after just one year of work. 

“The wharf deck is now being poured and the terminal increasingly taking shape. There is still plenty of work ahead, but these big milestones and visible signs of the progress being made across both projects.

“To maintain this progress, we have contracted our build partner for Bledisloe North, HEB, to roll straight onto delivery of the Fergusson North extension. Pre work for this project is already underway.

“Together, the new wharf and terminal will give Auckland better infrastructure for larger cruise ships while also increasing the port’s capacity for roll-on, roll-off freight. 

“In addition to these projects we’re extending Fergusson North and deepening the Rangitoto channel through our existing consent works package in 2027 – giving us the facilities to handle larger container vessels.” said Roger.

Port of Auckland is investing more than $200 million in infrastructure to make the port capable of handling larger cruise ships, container vessels and more roll-on, roll-off vessels. Both projects are scheduled to officially open in March 2027.

Background

  • Bledisloe North is being developed as Auckland’s first big-ship, multi-use wharf, supporting both cruise ships and roll-on, roll-off freight.
  • The wharf foundation is supported by 242 piles, which required more than 3,800m³ of concrete.
  • The deck comprises 290 precast concrete panels, approximately half cast on-site and half cast off-site.
  • Once the deck is complete, work will move on to wharf services and marine infrastructure, including fenders and bollards.
  • Construction of the cruise terminal is well into its internal fit-out, with ceilings, HVAC ductwork, cable trays, doors and fibre installation among the work already completed.